Digitalising desalination plants in the Canary Islands: what to measure before investing

A screen with graphs can help you operate a plant, but investment should start with a specific question: which decision do we want to improve? For a hotel, a farm, an industrial facility or an engineering company, selecting instrumentation for desalination plants in the Canary Islands means linking each measurement to production, water quality, maintenance or cost.

Sensor panel, flowmeter and monitoring screen alongside reverse osmosis equipment

What is new: greater attention to data and water efficiency

The report published by iAgua on 5 October 2026 covers contributions from the Government of the Canary Islands, EMALSA and EMMASA at the Spain Smart Water Summit, held from 29 September to 1 October. The Canary Islands session addressed planning, digitalisation and energy efficiency, with examples of remote management and operational information across the islands.

This is information about activities and trends in the sector. It is not a new call for grant applications or an instrumentation tender. For a private plant, its value lies in identifying which data are missing to justify a specific improvement, without automatically applying an urban water operator’s solutions to a small plant.

Which data are useful in a reverse osmosis plant?

DuPont’s digital RO operations manual includes flow rates, pressures, temperature, and feedwater and permeate quality as data for analysis. It also covers performance normalisation to compare different operating conditions. Each plant’s instrument list should be defined according to its design and needs.

DataUse in a reviewQuestion to clarify before supply
Feedwater, permeate and concentrate flow ratesRelate production to the distribution of water flows.Where will the measurement be taken, and what range must the instrument cover?
Pressures and pressure dropCompare how the identified sections are operating.Which points are being compared, and what connections are available?
Conductivity and temperaturePut water quality and process variations into context.Are the measurement location and the compensation applied recorded?
Electrical energy and usable water volumeCalculate an energy indicator with a defined scope.Does the meter cover only reverse osmosis, or also auxiliary equipment?
Shutdowns, cleaning and replacementsRelate maintenance interventions to the periods being compared.Who records each event and its cause?

Analytical instrumentation may include other parameters depending on pretreatment and the final use of the water. Measurement panels can group parameters such as pH, turbidity, chlorine, ORP or conductivity; selection should be based on the process, rather than a fixed list for every desalination plant.

If the main issue is permeate quality, also see our article on conductivity variations in reverse osmosis. The aim here is to prepare an investment in measurement and integration, rather than to replace fault diagnosis.

Cost per m³: separating energy costs from the total cost of water

To calculate the energy component, divide the kWh consumed during the period by the m³ for the same period and the same scope. If you want to compare usable water delivered, the denominator must reflect that volume; avoid mixing it with gross production or with different periods.

Illustrative example only

A set of equipment consumes 360 kWh and delivers 120 m³ during a given period: the indicator is 3 kWh/m³. At an assumed electricity price of €0.15/kWh, the energy component would be €0.45/m³. These figures do not describe a HidroSoluciones plant or a contracted electricity tariff in the Canary Islands.

This calculation is not the total cost of water. To assess an investment, you also need to decide how to account for consumables, maintenance, cleaning, labour and depreciation. Documenting these rules makes it possible to compare an instrumentation proposal with other options, such as repairing equipment or improving pretreatment.

How to plan an improvement in phases

First, take stock of what is already installed

Gather instrument model details, available signals, control panel information and diagrams. Identify which measurements are read manually, which are recorded and which are not used. Before buying new sensors, clarify whether you need to measure, record, transmit or interpret information that is already available.

Then, agree the scope with the system integrator

Define responsibilities for installation, wiring, configuration and data delivery. Specify who receives alarms and how the work will be accepted. Remote access, if included, requires agreeing user accounts and permissions with the owner and their IT manager; it should not be assumed when quoting an instrument.

Finally, acceptance and follow-up

A comparable quotation should explain how readings will be checked, what documentation will be provided and who will maintain the system. Agree a review of the results while the plant is operating under representative conditions. New data recording can support decisions, but by itself it does not guarantee savings or establish the cause of a deviation.

What to send when enquiring about supply or local technical support

  • Island and plant location, water use and the purpose of the improvement.
  • Flow rate, water analysis and available records, with dates and units.
  • Photographs of connections, instruments and control panels; model details and diagrams where available.
  • Required scope: supply, replacement, installation, integration or maintenance.
  • Planned timescales and any access or shutdown restrictions.

These details are useful both for plant managers and for engineering and construction companies from mainland Spain working on projects in the Canary Islands. They help define the enquiry without assuming a solution, an available grant or quantified savings.

HidroSoluciones Canarias offers instrumentation, spare parts and maintenance for desalination plants, as well as a Plan Renove programme to assess upgrades to existing plants. The scope and terms of any proposal must be checked for each case.

Sources

Discuss the instrumentation your plant needs

Send us the location, flow rate, existing equipment, available records and the purpose of the improvement. This information will help us assess an enquiry about supply, replacement, installation or technical support in the Canary Islands.

Enquire about supply or technical support

FROM TECHNICAL CRITERIA TO YOUR PROJECT

Do you want to apply these criteria to your installation?

Water treatment for industry, hotels, agriculture, and public services. From the Canary Islands, we study the needs of projects in Latin America and Africa based on water quality, flow rate, and operating conditions.

Tell us the location, the source of the water, and the purpose of your project to guide the technical consultation.

Consult my projectExplore more technical guides
Scroll to Top